- Budget range
- $625K – $820K
- TI + FF&E, excl. equipment finance
- Timeline
- 9 – 13 months
- Lease exec → CO, most likely
- Jurisdiction note
- Placer County plan check
- Budget 6–10 wks, two rounds typical
- Title 24
- Required — MEP scope
- Factor into MEP engineer fees
- Electrical service. 2nd-gen retail may not have panel capacity for 4 ops + compressor.
- Landlord TI gross-up. Confirm $ are net of landlord supervision fee and management overhead.
- Plumbing below slab. No central vacuum or drain rough-in visible — verify before design starts.